Saturday, December 17, 2011

Two tiring days of work on the KHall site!

I'm going to attach two days of pictures in one post.  I worked on the site Thursday and Friday.

Wow am I NOT used to working that hard!  Thursday, I spent a good part of the day cutting rebar to the sizes we'll need for the footings, walls and other portions of the building.
Friday I was all over the place.  Rebar cutting, bending, shoveling gravel/coral to put in the footing trenches and unloading 100 pound bags of concrete from the delivery vendor!  It felt like the day was never going to end!  But Jehovah blessed us with a nice sunset that evening to watch so that was nice.

Today (Saturday) I'm catching up with all my other tasks that didn't get taken care of over the last few days while working on the site.  I hope you like the pictures.




 Cutting Rebar to size




 
Russell, The Rebar Bending Expert!

 
Duane Lee and I bent those rebar all by ourselves!




Vince Perez with the compactor




Thats all for now!  More pictures soon!

Sunday, December 11, 2011

Kingdom Hall work started!



On Saturday, we started actual construction preparations on the new site which was pretty exciting.  We had 5 flatbed trucks along with a semi-truck as we brought things from the branch down to the site, also two containers arrived from the completed project in Ebeye, Marshall Islands.  Attached are some pictures both from the morning when we were just starting and what it looked like when I left at about 3PM. I'll try to keep this blog updated as we go through the project.  Lanny