Monday, February 6, 2012

Picture of the Week: Picture of the Week

Picture of the Week: Picture of the Week: Yesterday's meeting with our zone overseers included as nice an interview as I've heard in quite awhile; at least since the last one....

Thursday, January 5, 2012

2011-12-29

Footings have been poured and now its time to line up where the block will go...





 Digging out the forms from off the footings was a real job!


 Installing the steel cages that will become the columns of the building.
 Putting the forms around the cages to get them ready to be poured.


 Bending the rebar out of the way so the forms can fit around the cages


 The new work shed areas.  Two tool containers and a semi covered work area for fabrication.
Hope you enjoyed.

2011-12-22

Worked at the Kingdom Hall project some more and took these shots.




These are the steel cages that will have poured concrete around them to form the colums

Saturday, December 17, 2011

Two tiring days of work on the KHall site!

I'm going to attach two days of pictures in one post.  I worked on the site Thursday and Friday.

Wow am I NOT used to working that hard!  Thursday, I spent a good part of the day cutting rebar to the sizes we'll need for the footings, walls and other portions of the building.
Friday I was all over the place.  Rebar cutting, bending, shoveling gravel/coral to put in the footing trenches and unloading 100 pound bags of concrete from the delivery vendor!  It felt like the day was never going to end!  But Jehovah blessed us with a nice sunset that evening to watch so that was nice.

Today (Saturday) I'm catching up with all my other tasks that didn't get taken care of over the last few days while working on the site.  I hope you like the pictures.




 Cutting Rebar to size




 
Russell, The Rebar Bending Expert!

 
Duane Lee and I bent those rebar all by ourselves!




Vince Perez with the compactor




Thats all for now!  More pictures soon!

Sunday, December 11, 2011

Kingdom Hall work started!



On Saturday, we started actual construction preparations on the new site which was pretty exciting.  We had 5 flatbed trucks along with a semi-truck as we brought things from the branch down to the site, also two containers arrived from the completed project in Ebeye, Marshall Islands.  Attached are some pictures both from the morning when we were just starting and what it looked like when I left at about 3PM. I'll try to keep this blog updated as we go through the project.  Lanny